News & Events - 2005
As a company, Red Fork Production is in the business of Resource Balancing. We are deeply affected by the balance of nature, both above ground and below. We work very closely with our land and our mineral owners, and are very careful to create a positive impact in our operations. We exercise more care and prudence than is expected of us by the various regulatory agencies, not because we are forced, but because we believe. We initiate, develop and maintain a mutually beneficial relationship with our surface and mineral resource partners. We are cognizant of their concerns, and we initiate many permanent improvements to their domain. In addition, all phases of our operations are geared toward protecting the Asset, and we exercise every practice to conserve and maximize reservoir drainage to achieve the greatest recovery of our planet’s scarce hydrocarbon reserves.
2005
11.16.2005
Rig up Workover unit on Hunn # 34-1. Long stroke pump, good pump action. Rig down.
11.10.2005
Repair Pump Jack on Hunn # 34-1, but cannot hook rods up to bridal. Pump is hung up. Will require a Workover rig.
11.2.2005
Pump hangs up on Hunn # 34-1, sheers off Pitman arm pin, walking beam collapses. Shut in well.
10.29.2005
Line repaired on Hunn # 34-1, re-buried, start Pump Jack, well to sales.
10.28.2005
Adjust weights on Hunn # 34-1, start well. Flow line leaks and Electrician cut line. Repair line.
10.27.2005
Several attempts to start Pump Jack on Hunn # 34-1, unsuccessful.
10.26.2005
Finish bailing sand on Hunn # 34-1 well. Run 2-3/8” tubing into well, set at 3,773’. Run single rods and new pump into well, set and adjust Pump Jack. Counterbalance out of balance, can’t start well.
10.25.2005
Hook up frac tank on King # 23-1 well. Open well to flow frac fluids back into tank. Install 2-phase separator to Scissortail sales line.
Rig up to bail sand out of Hunn # 34-1 well. Clean out 30’.
10.24.2005
Move in, rig up Workover unit on Hunn # 34-1 well. Run in hole with 2-3/8” Tubing, tagging sand at 3,786’ (94’ of sand in hole). Pulled tubing back out of hole.
Make preparations with Scissortail Energy about the gas sold out of the King # 23-1. Start gas test with Scissortail.
10.22.2005
Replace electrical parts damaged by storm at the Hunn Salt Water Disposal System.
Arrive King # 23-1, hook pump truck up to casing and circulate hole clean. Pull tubing bit sub and bit out of hole. Rig up Electric Wireline unit, perforate Gilcrease sand. Run in tubing to TD, circulate 65 Bbls clean salt water to pit. Pull 3 swabs.
10.11.2005
Finish stringing and hooking up electric motor and panel on King # 23-1 well. Start Pump Jack, adjust and calibrate.
9.30.2005
Finish meter runs and splitters on King # 23-1 sales facility and set Pump Jack.
9.29.2005
Working on sales facility for the King # 23-1, building manifold for gas lines, moving, calibrating and resetting gas separators.
9.23.2005
Tanks full from fluids produced from Hunn # 34-1 well flowback. Empty and continue with flow back after fracture treatment.
9.21.2005
Finish installation and pressure testing of flowlines for Hunn # 34-1. Open to test tank.
9.19.2005
Continue working on flow line and tanks on Hunn # 34-1.
9.16.2005
Trench and lay flow lines from Hunn # 34-1 to sales facility. Pressure test all equipment at gathering station. Repair gun barrel.
9.10.2005
Rig up wellhead and flowline on Hunn # 34-1 well, flow back frac to tank.
9.9.2005
Conduct Hydraulic Fracture on Hunn # 34-1 well.
9.7.2005
Flow King # 23-1 to pit for seven days to clean out reservoir.
9.6.2005
Move stimulation equipment into King # 23-1 location, conducT hydraulic fracture treatment on well.
9.2.2005
Conduct casing swab operations on King # 23-1 well, make ready for frac.
8.30.2005
Move in Workover Rig to Hunn # 34-1 well, conduct casing swab operations to prepare well for fracture treatment.
8.24.2005
Move in Electric Line unit to King # 23-1 well, run Cement Bond Log, perforate Woodford Shale.
8.15.2005
Run Electric Logs in King # 23-1 well.
8.14.2005
Arrive @ Test Depth, drilling complete on King # 23-1 well.
8.4.2005
Spud Drilling Rig over King # 23-1 well @ 8PM, drill Rat Hole & 12¼” surface hole. Continue drilling operations.
8.3.2005
Move in Electric Line unit on Hunn # 34-1 well, conduct Cement Bond Log, then perforate Woodford Shale.
Bring rig into location, erect Rig to drill King # 23-1 well. Continue assembly of rig components.
8.2.2005
Continue construction operations on King # 23-1 location.
8.1.2005
Obtain Restraining Order against land owner from Judge Larry Parrish and Sheriff supervision. Resume operations on King # 23-1 drill site, building pits, roads, pad.
7.29.2005
Commence building roads and location into King # 23-1 well, landowner representative brandishes gun. Red Fork orders construction workers out.
7.28.2005
Courier files Surface Damage Lawsuit in Okfuskee County District Court, Okemah, Oklahoma.
7.27.2005
Drilling rig attempts to move in to drill King # 23-1 well, landowner refuses to honor Surface Damage Agreement and denies access.
7.23.2005
Run Electric Logs, cement casing in Hunn # 34-1 well.
7.21.2005
Arrive @ Test Depth, drilling complete on Hunn # 34-1 well.
7.12.2005
Move in Drilling Rig, spud and commence drilling Hunn # 34-1 well.
7.11.2005
Finish rigging up Drilling Rig, continue to reinforce pits and tanks. Drill Rat hole and insert sleeve.
7.10.2005
Move in remainder of Drilling Rig, commence rig up and leveling operations for Hunn # 34-1 location. Position pipe racks, casing arrives. Lay water lines to tank.
7.9.2005
Continue pad and mix pit construction. Begin move in Drilling Rig components.
7.8.2005
Same, cut path over hill for water line to spring fed pond.
7.6.2005
Shooting grade on pad and continues leveling operations and pit construction on Hunn # 34-1 location.
7.5.2005
Continue pad and pit construction at Hunn # 34-1 location.
7.4.2005
Continue building road into Hunn # 34-1 location, commence on earthen pits.
7.3.2005
Continue building road into location.
7.2.2005
Continue building road, location will be on a hillside.
7.1.2005
Building road into Hunn # 34-1 well location.
6.26.2005
Finish running rods into Wise # 26-1 well, mount and balance pump jack with gas engine. Commence long term test on well with flow line to pit. Pumper checks well daily.
6.24.2005
Move in, rig up Workover rig on Wise # 26-1. Install tubing, pump and rods. Secure well.
6.12.2005
Continue to swab Wise # 26-1 well to pit. Rig down Workover. Rig up flowline and flow well to pit, unattended.
6.11.2005
Rig up Workover, conduct swabbing operations on Wise # 26-1 to pit.
6.10.2005
Move in, rig up Pumping Units, Mixers and Blender on Wise # 26-1 well, position Frac Van and Tanks, pressure test lines, commence with 15% HCL Acid flush, followed with injection of 331 Bbls gelled water with 8,000 lbs. of 20/40 Ottawa sand. Rig down equipment, secure well.
6.3.2005
Move in Workover rig, swab the Wise # 26-1 well to remove spenT acid. Inject fluid into well through perforations into reservoir. Rig up Electric Log unit and conduct Temperature Survey to trace path and migration and design Hydraulic Fracture Treatment. Rig down, secure well.
5.25.2005
Move into Wise # 26-1 with pressure equipment, conduct Acid Treatment. Rig down, secure well.
5.24.2005
Move in, rig up Workover rig, Electric Line unit. Conduct Cement Bond Log, evaluate. Pull out of hole, arm casing guns, run back in hole and perforate Wise # 26-1 well. Swab load water and fluids back.
5.19.2005
Drill out cement with Power Swivel on Wise # 26-1 well. Rig down equipment, secure well.
5.18.2005
Move in, rig up Workover unit and pressure equipment to pump cement on Wise # 26-1.
5.11.2005
Recommend against pursuing completion further. Overruled.
5.5.2005
Evaluate results of Reservoir treatment on Wise # 26-1.
5.3.2005
Conclude swabbing operations on Wise # 26-1, run back in hole with tubing, secure well.
4.28.2005
Continue swabbing operations on Wise # 26-1, test and drift tubing.
4.27.2005
Able to resume Swabbing operations on Wise # 26-1 well. Benzoid acid flakes not dissolving, swabbing back in consolidated form.
4.25.2005
Continue Swabbing operations on Wise # 26-1 well. Rig Electric Line unit, log well. Have to shut down due to severe lightning and thunderstorms.
4.23.2005
On Wise # 26-1 well, rig up slick line unit and run in hole with Overshot Tool, catch fish (Temperature Logging Tool) and pull out of hole. Rig up Workover unit and resume Swabbing operations.
4.22.2005
Rig up High Pressure Pumping Units on Wise # 26-1 well, perform diverting operation with Benzoid Acid flakes. Rig up Wireline Unit, run in hole with Temperature Logging Tool to track injection path of Magnalyte. Temperature Logging Tool stuck in hole, pull out of rope socket.
4.21.2005
Rig up Workover unit on Wise # 26-1 well, swab acid and load water back. Prepare well for Magnalyte Treatment.
4.20.2005
On Wise # 26-1 well, drill out cement in Casing using Power Swivels. Rig up Electric Line unit, perforate well. Rig down E-Line, rig up high pressure pump equipment and conduct Acid Stimulation job. R/D equipment.
4.19.2005
Move in, rig up Workover unit over Wise # 26-1 well. Pull tubing, drift and test. Remove Pump, test and refurbish. Rig up Electric Line, log well, set Bridge Plug, and perforate well @ 600’ for Squeeze Job.
4.15.2005
Pressure test and conduct Mechanical Integrity Test (MIT) on Wise # 26-1. Passed test.
4.14.2005
Move in cementing equipment to Wise # 26-1 well for re-completion. Rig up cementers, perform squeeze job on subject well.