Red Fork Production, LLC
News & Events - 2007
As a company, Red Fork Production is in the business of Resource Balancing. We are deeply affected by the balance of nature, both above ground and below. We work very closely with our land and our mineral owners, and are very careful to create a positive impact in our operations. We exercise more care and prudence than is expected of us by the various regulatory agencies, not because we are forced, but because we believe. We initiate, develop and maintain a mutually beneficial relationship with our surface and mineral resource partners. We are cognizant of their concerns, and we initiate many permanent improvements to their domain. In addition, all phases of our operations are geared toward protecting the Asset, and we exercise every practice to conserve and maximize reservoir drainage to achieve the greatest recovery of our planet’s scarce hydrocarbon reserves.
2007
12.22.2007
Semcrude Transport Truck # 4033 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 12:33. Observed API of oil is 35.0 degrees. BS&W % = 2.00%
[ Ticket # 1631386 ]
12.21.2007
Negotiated with Legacy Energy and Vastar Resources to extend an include additional acreage to drill Grace # 25-6 and Grace # 24-1 wells.
12.18.2007
Chesapeake Energy elects to participate in the Grace # 25-6 well, as per Pooling Order. Red Fork Production will drill, complete, produce and operate the well and Chesapeake Energy will be a Working Interest Partner.
12.17.2007
Semcrude Transport Truck # 4067 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48752, Creek County, Oklahoma @ 10:20. Observed API of oil is 33.8 degrees. BS&W % = 6.00%
[ Ticket # 1877407 ]
12.14.2007
Chesapeake Energy elects to participate in the Grace # 24-1 well, as per Pooling Order. Red Fork Production will drill, complete, produce and operate the well and Chesapeake Energy will be a Working Interest Partner.
12.5.2007
Run rest of rods in Grace # 25-5 and spaced pump.
12.4.2007
Move into Grace # 25-5 well, rig up Workover unit. Run in hole with tubing, TD @ 3400’, perforations @ 3348 – 3360’. Tally in tubing & 18’ Mud Anchor. Tag frac sand @ 3375’. Pull up, set SN at 3354’ . Run in 10’ 1 ½” cup and ring pump, ¾” rods. Secure well, leave location.
Run in cup, ring, rods and pump on Grace # 25-4 well. Install and pressure test wellhead. Rig down Workover unit. Secure well, leave location.
12.3.2007
MIRU Workover unit on Grace # 25-4 well. 25# on surface, blow down, bleed off. Run in hole with tubing, Seating Nipple @ 3,339’ w/ 18’ Mud Anchor. Secure well.
12.1.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 12:55. Observed API of oil is 35.1 degrees. BS&W % = 1.50%
[ Ticket # 1720950 ]
Adjust and start Pump Jack on Hunn # 34-4 well. Well is producing gas to sales line and frac fluids to tank. Will continue clean up until frac fluids are gone.
11.29.2007
Deliver, set and install Pump Jack over Hunn # 34-4 well. Trench, string and connect electricity to wellsite.
11.28.2007
Move in to Grace # 25-4 location, rig up high pressure hydraulic fracture and pump equipment, transports, rig up, pressure test lines to 1,000#. Proceed to inject 276 Bbls of gel and frac fluid, along with 9,700# of 20/40 Ottawa sand, at pressures of up to 1,100#. Shut in, secure well, rig down heavy iron and leave location.
11.27.2007
Rig up Workover unit on King # 23-1, perform tubing swab. Hook well up to sales line. Turn on well to sales
11.26.2007
Blow well down, finish swab operations on Hunn # 34-4. Install Rods and Pump in well. Hook up well head and re-connect well to sales. Rig down W/O rig.
11.25.2007
Continue recovery of frac fluids through tubing swabbing operations on Hunn # 34-4 using W/O rig.
11.24.2007
Move in W/O unit, rig up on Hunn # 34-4. Install production tubing in well. Conduct swab operations through tubing.
11.23.2007
Move in Workover unit to Hunn # 34-4, tally tubing, run tubing and seating nipple in hole. Perform tubing swab. Shut well in. Leave location.
Workover unit finish swabbing on Grace # 25-5. Shut well in, leave location.
11.21.2007
Move Workover unit to Grace # 25-5 and perform casing swabbing operations.
Move in rig up Workover unit, pull tubing and rods, prepare Grace # 25-4 for fracture treatment.
11.20.2007
Survey well location and well elevation for Grace # 25-6.
11.19.2007
Second D-6 Dozer filling pits and building road to Grace # 25-5 (20 hrs).
Clear Right of Way through rock, hill and timber with D-6 Dozer for Electric lines to supply Grace # 25-3 and Grace # 25-4 (75 hours).
11.15.2007
Semcrude Transport Truck # 4067 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48752, Creek County, Oklahoma @ 09:25. Observed API of oil is 35.9 degrees. BS&W % = 0.30%
[ Ticket # 1877287 ]
11.6.2007
Start Pump Jack on Grace # 25-4, set and adjust.
11.5.2007
Continue trenching and laying flow lines from Grace # 25-4 to sales facility.
11.4.2007
Semcrude Transport Truck # 4067 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 17:15. Observed API of oil is 39.0 degrees. BS&W % = 0.40%
[ Ticket # 1877252 ]
11.2.2007
Move in, install pump jack on Grace # 25-4 well. Set and adjust unit, lay flow lines and connect to wellhead.
10.31.2007
Prepare Hunn # 34-4 well for frac. Conduct Hydraulic Fracture Treatment on subject well. Move equipment out.
10.30.2007
Move Workover rig into Grace # 25-4 well, install wellhead, 2-3/8” tubing, downhole pump and rods. Rig down Workover unit.
Replaced grease hose on saddle bearing on Grace # 25-3 pumping unit.
Changed oil and pulled shim on rod bearing on Grace # 25-6. Well is making 2-4 BOPD.
10.28.2007
Well head pressure on Hunn # 34-4 up to 500#. Open well, flowing gas to sales.
10.27.2007
Move into Grace # 25-5 well, rig up Workover Rig for swabbing operations. Open valve, well on vacuum. 600’ fluid in hole. Swab well, good show oil, very slow fluid entry. Shut well In.
Grace # 25-4 has 40# at surface. Commence swabbing operations, tag fluid @ 1,000’, pull from 75’ has oil on top, good gas blow, gas getting stronger. Shut well in, rig down Workover unit, arrange for tubing, rods and pump.
10.26.2007
Move Workover unit into Grace # 25-4 well, conduct casing swab, prepare well for and commence pumping Acid stimulation into Union Valley formation. Swab well till clean of acid. Swabbing from TD, getting good shows oil, gas and load water. Shut in, secure well.
Install wellhead on Hunn # 34-4 well, connect and trench flowline to sales facility. Open well to sales line, selling gas.
10.25.2007
Rig up Workover unit on Grace # 25-3 well. Pump water down tubing and casing to kill well. Pull rods and pump out of hole. Load tubing with water. Hang well on, rig down.
Rig up Workover unit, install 4 ½” Orbit Valve on casing at Grace # 25-4.
Check pressure on King # 23-1 well. Rig up Workover unit, swab well back through tubing. Lay down swab. Plumb well in, rig down W/O.
10.24..2007
Move in Workover rig to King # 23-1. Open well, well starts flowing. Call pump truck to kill well. Tally and pull tubing out of hole. Run tubing and packer back in hole. Swab well down through tubing. Shut in well.
10.21.2007
Semcrude Transport Truck # 4080 picks up load(s) oil from Grace # 25-1, Red Fork Production Tank # 48430, Okfuskee Co., Oklahoma @ 08:42. Observed API of oil is 40.0 degrees. BS&W % = 0.20%
[ Ticket # 1631164 ]
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-1, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 08:39. Observed API of oil is 40.0 degrees. BS&W % = 0.40%
[ Ticket # 1631163 ]
10.20.2007
Move in, rig up Workover rig on King # 23-1 well. Rig up, conduct swabbing operations through tubing. Blew casing down. Pulled 3 joints tubing out of hole. Packed well off, shut in, leave location.
10.19.2007
Re-working lease road leading up steep hill to Grace # 25-1 (31 hours).
Hunn # 34-4 well head pressure up to 500#; blow down well and shut in. Continue to monitor build-up pressures.
10.18.2007
Move in Workover Rig, casing swab Hunn # 34-4 well, conduct flow tests. Rig down Workover unit. Shut well in for surface build up test.
10.17.2007
Rig up Workover unit on Hunn # 34-4. Unload well with casing swab operations. Rig down, leave location.
10.15.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 49607, Okfuskee Co., Oklahoma @ 10:20. Observed API of oil is 36.8 degrees. BS&W % = 0.30%
[ Ticket # 1820370 ]
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 49606, Okfuskee Co., Oklahoma @ 10:17. Observed API of oil is 36.8 degrees. BS&W % = 0.30%
[ Ticket # 1820369 ]
10.10.2007
Move onto Grace # 25-4 well with Electric Wireline, run Cement Bond Log and perforate Union Valley Cromwell using two Casing gun runs, 3,306 – 3,312’ and 3,295 – 3,301’, 4 shots per foot. Rig down Anline, secure well, leave location.
10.9.2007
Appear in County Court for Newby # 6-2 Pooling and Spacing hearing.
10.8.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 49606, Okfuskee Co., Oklahoma @ 10:17. Observed API of oil is 36.0 degrees. BS&W % = 4.0%
[ Ticket # 293442 / Rejected ]
Rig up Workover unit on Grace # 25-4 well. Blow casing down. Install tubing head, tubing, rods and new pump in hole. Seat and space out pump. Rig down, leave location.
10.4.2007
Drag equipment out of Grace # 25-4 location with D-6 Dozer, level and smooth out ruts, secure pits.
10.2.2007
Move in fracture equipment to Grace # 25-5. Rig up, pressure test lines and frac heads, surface equipment, to 2,000#. Rig up KCL, Gel water trucks, Mixers and Blenders. Well has 100# @ surface, bleed off for 1.5 Min. w/strong blow. Pump frac @ 1,350#, 278 Bbls. frac fluid, total sand flushed to perfs: ISIP 900 #, 5 Min 775 #, 10 Min 700 #, 15 Min 700 #, shut in, secure well. Rig down Svc Companies.
Run Electric Logs, cement casing in Grace # 25-4 well.
10.1.2007
Make preparations to frac Grace # 25-5 Union Valley Cromwell. Bring in water transports to location, arrange arriving equipment.
Arrive @ Test Depth, drilling complete on Grace # 25-4 well.
9.30.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 07:40. Observed API of oil is 37.2 degrees. BS&W % = 0.20%
[ Ticket # 1720848 ]
9.28.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 12:54. Rejected load because 100% BS&W. [ Ticket # 293438 ]
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 08:34. Rejected load because 80% BS&W. [ Ticket # 293437 ]
9.26.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48752, Creek County, Oklahoma @ 15:35. Observed API of oil is 37.2 degrees. BS&W % = 0.30%
[ Ticket # 1130040 ]
9.25.2007
Move in Drilling Rig, spud and commence drilling Grace # 25-4 well.
9.24.2007
Build roads, location, pits and pad for Grace # 25-4 well.
9.22.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 11:50. Observed API of oil is 38.0 degrees. BS&W % = 0.20%
[ Ticket # 1720828 ]
9.18.2007
Continue to work on, calibrate Hunn # 34-2 Pump Jack; start unit, selling gas.
Continue swab job, then conduct Acid job on Hunn # 34-4 well. Swab acid out of well, recover load, good gas show. Shut-in well, rig down W/O.
9.17.2007
Move in Workover Rig to Hunn # 34-4 well, rig up to well.
Run in hole on Hunn # 34-2 well with rods and pump and new string 2-3/8” tubing and new mud anchor. Check pump action and hang well on.
9.14.2007
Move in W/O unit to Hunn # 34-2 well. Pull rods and pump out of hole. Blow casing down. Pull tubing out of hole, shut well in.
Get back on Grace # 25-5 well. Resume swabbing operations. 30# on surface, blow well down. On first run, pull 300’of fluid. Pull gets 250’ gas ahead of swab, 50’ live oil on top. 2nd swab run no fluid. 100’ gas ahead of swab. Shut in, secure well. Rig down WO unit.
9.13.2007
Blow down pressure off of Grace # 25-5 well. Rig up Workover and swab well down. Shut in well.
9.12.2007
Move Workover rig and frac equipment into Grace # 25-5 by dozer. Rig up W/O, perform casing swab. Conduct acid treatment. W/O swab acid back. Shut well in.
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-1, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 12:34. Observed API of oil is 40.1 degrees. BS&W % = 0.50%
[ Ticket # 1820123 ]
9.11.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48752, Creek County, Oklahoma @ 11:32. Observed API of oil is 36.1 degrees. BS&W % = 0.70%
[ Ticket # 1130011 ]
9.7.2007
Move Workover rig onto Grace # 25-5 location. Pull rig in with dozer. Rain storm forced cancellation of job.
9.6.2007
Grace # 25-1 still flowing. Hook up pump truck to kill well. Run in tubing, pump and rods. Start Pump Jack, producing both zones. Rig down Workover unit.
9.5.2007
Remove plug from Grace # 25-1 to prepare to commingle Union Valley and Gilcrease zones.
9.4.2007
Move in Workover unit to Grace # 25-1, pull tubing and rods.
Run Electric Logs, cement casing in Grace # 25-2 well.
9.3.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-3, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 12:34. Observed API of oil is 35.5 degrees. BS&W % = 0.60%
[ Ticket # 293433 ]
Arrive @ Test Depth, drilling complete on Grace # 25-2 well.
9.1.2007
Run in pump on Hunn # 34-2 well. Restart and monitor.
8.31.2007
Pump hung up again on Hunn # 34-2, bring in Workover unit, pul rods and pump out of hole, inspect. Perform tubing swab. Shut well in.
Complete casing swab on Hunn # 34-4 well. Rig down W/O unit.
8.30.2007
Move in Workover unit, conduct casing swab to test tank on Hunn # 34-4 well. Slight show of gas. Shut well in.
Jar pump and commence pumping on Hunn # 34-2 well; rig down Workover unit.
8.29.2007
Move in, rig up Workover unit and install new pump, rods and tubing into Hunn # 34-2 well. Check and calibrate pump action.
8.28.2007
Move in Drilling Rig, spud and commence drilling Grace # 25-2 well.
8.23.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-1, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 08:42. Observed API of oil is 41.2 degrees. BS&W % = 0.20%
[ Ticket # 1820123 ]
8.22.2007
Rig up Electric Line unit, perforate Hunn # 34-4 well in lower Union Valley with casing gun/ 4 holes per foot.
Rig up equipment on Hunn # 34-2, Acidize Union Valley formation.
Move in rig up Electric Line Unit on Grace # 25-5 well. Run in hole, conduct Cement Bond Log. TD at 3408.6, Top of cement 3030’ (cement fill of 378.6’) Pull out of hole, arm casing perforating gun, Run in hole and perforate Union Valley Cromwell (3348’ - 3354’), pull out of hole, re-arm, Run back in hole for second set (both @ 4 shots/foot). Perforate w/casing gun 3356’ - 3360’. Rig down Anline Logging, move in, cut top of casing clean, weld on casing head. Install valve, shut in, secure well.
8.21.2007
Semcrude Transport Truck # 4130 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 14:18. Observed API of oil is 38.9 degrees. BS&W % = 0.40%
[ Ticket # 1850077 ]
8.7.2007
Semcrude Transport Truck # 4067 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48752, Creek County, Oklahoma @ 12:49. Observed API of oil is 38.0 degrees. BS&W % = 0.10%
[ Ticket # 1870081 ]
Semcrude Transport Truck # 4067 picks up load(s) of oil from Newby # 6-1, Red Fork Production Tank # 48753, Creek County, Oklahoma @ 12:24. Observed API of oil is 38.0 degrees. BS&W % = 0.10%
[ Ticket # 1870080 ]
7.31.2007
Pull Drilling Rig off Grace # 25-5 well with D-6 Dozer, level pad and roads.
7.30.2007
Semcrude Transport Truck # 4131 picks up load(s) Grace # 25-1 oil, Red Fork Production Tank # 48430, Okfuskee Co., Oklahoma @ 12:01. Observed API of oil is 42.0 degrees. BS&W % = 0.20%
[ Ticket # 1820038 ]
Semcrude Transport Truck # 4131 picks up load(s) Grace # 25-1 oil, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 11:54. Observed API of oil is 42.0 degrees. BS&W % = 0.20%
[ Ticket # 1820037 ]
7.27.2007
Run Electric Logs, cement casing in Grace # 25-5 well.
7.26.2007
Arrive @ Test Depth, drilling complete on Grace # 25-5 well.
7.23.2007
Rig up Electric Line, run Cement Bond and Chlorine Logs on Hunn # 34-4 well.
7.20.2007
Move in Drilling Rig, spud and commence drilling Grace # 25-5 well.
Hook up flow line to well head on Hunn # 34-3 well. Open well to sales line; selling gas.
7.19.2007
Run Electric Logs, cement casing in Hunn # 34-4 well. Brought in two D-6 Dozers to help drag equipment off location, then rework roads.
7.18.2007
Rig up Workover unit and kill truck to Hunn # 34-3 well. Perforate Red Fork sand. Run tubing, rods and pump in well. Plumb in flowline.
7.17.2007
Deliver and spread 2 loads crusher run and 8 loads of 3” rock to build the road into Grace # 25-5 well. (5 days)
7.16.2007
D-6 Dozer worked four days clearing location and reserve pit area, then building location and dig working pit for Hunn # 34-4 well.
7.14.2007
Five days to excavate, level, drain and build location for Grace # 25-5 with D-6 Dozer. Had to cut terraces to drain standing water, place 39.7’ X 20” steel pipes for semi-permanent spillovers.
7.12.2007
Rig up Workover Unit, pull tubing and rods out of Hunn # 34-2 well to prepare for Acid job.
7.9.2007
Move in Drilling Rig, spud and commence drilling Hunn # 34-4 well.
Deliver tubing, rods and well head to Hunn # 34-3 location.
7.2.2007
Semcrude Transport Truck picks up first load(s) Grace # 25-1 oil, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 13:24. Observed API of oil is 40.6 degrees. BS&W % = 6.0%
[ Ticket # 118001519 ]
6.25.2007
Survey well location and well elevation and stake location on Hunn # 34-4 well.
6.13.2007
Move Workover rig onto Hunn # 34-1, rigged up. Well is on vacuum. Install Tubing head. Attempt to run tubing into hole but well is live. Install stripper rubber and run new pump and rods in hole. Seat and space pump. Hang well.
6.8.2007
Perform Hydraulic Fracture treatment on Hunn # 34-1 in the Union Valley formation.
6.4.2007
Rig up Workover unit on Hunn # 34-1, pull tubing, rods and pump out of hole. Break out wellhead, replace with casing swage. Shut in, secure well.
6.2.2007
Rig up Workover rig on Hunn # 34-2, pull tubing, rods and pump out of hole. Install swage and valve in casing. Rig down.
6.30.2007
Semcrude Transport Truck # 1267 picks up load(s) Grace # 25-1 oil, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 12:11. Observed API of oil is 39.3 degrees. BS&W % = 0.30% [ Ticket # 510004896 ]
On Newby # 6-1, inject 100 gallons acid / 26 Bbls. lease oil via annulus @ 1,150#.
5.24.2007
Survey well location and well elevation, stake wellsite for Newby #6-2.
5.23.2007
Semcrude Transport Truck # 4131 picks up load(s) oil from Grace # 25-1, Red Fork Production Tank # 48429, Okfuskee Co., Oklahoma @ 09:36. Observed API of oil is 40.2 degrees. BS&W % = 12.50%
[ Ticket # 710006196 ] Rejected Load: Too much BS&W
5.22.2007
Finish production test on Grace # 25-3 well and re-plumb well head and sales line.]
5.21.2007
Conduct Enerfin 24 hour gas production test on Grace # 25-3.
5.17.2007
Move Workover rig onto Grace # 25-1. Run Tubing, Mud Anchor, Seating Nipple, and Rods in hole. Seat and space out pump, hang well, turn on and divert to sales.
Finish running in tubing, rods and pump on Grace # 25-3 well. Set pump, hook up well head, connect flow lines. Rig down W/O unit.
5.16.2007
Load casing on Newby # 6-1 with salt water.
Rig up Workover rig on Grace # 25-3 well. Casing swab well, install 4 ½” Orbit Valve on casing. Well kicks and starts flowing during swab. Direct flow to test tank. Died down. Run Mud Anchor, seat nipple, 20 joints tubing. Well kick off again, flowing. Connect to flow line and turn well to sales. Leave location.
4.20.2007
Move in, conduct fracture treatment on Grace # 25-3 well. Use D-6 Dozer to drag equipment up hill to work site.
Move in frac equipment to Grace # 25-1 well, conduct fracture treatment in Gilcrease formation. Rig down equipment, move over to Grace # 25-3 well. Had to use D-6 Dozer to drag water truck and pump trucks up hill because of rain.
4.19.2007
Run Casing swab on Grace # 25-1 well. Swab well dry. Rig up, perform acid stimulation. Swab well back. Rig down Workover unit.
4.18.2007
Move in Workover unit to Grace # 25-1, pull tubing, rods and pump. Conduct Acid stimulation injection into Gilcrease formation.
4.17.2007
Move in Workover rig, pull tubing, rods and pump from Grace # 25-3 well. Break off wellhead, install 4 ½” Orbit Valve. Rig down W/O.
4.16.2007
Move in Workover rig to Grace # 25-1 well, pull rods, pump and tubing. Remove wellhead, install Orbit Valve on Casing. Secure and shut well in.
4.12.2007
Deliver Quincy Rental Compressor to Hunn Lease, set up, calibrate and put into service.
3.29.2007
Blow down excess pressure from Grace # 25-1 well. Conduct casing swab. Install new well head and strip in tubing, rods and pump. Rig down. Turn on pump to clean well and sale oil to tank.
3.26.2007
Rig up Workover unit on Grace # 25-1 well.
3.15.2007
Rig up Electric Wireline Unit on Grace # 25-1 and set Bridge Plug @ 3,410’. Perforate Gilcrease sand. Shut in well, rig down.
3.10.2007
Rig up Workover unit on Grace # 25-1, pull tubing and rods, rig down.
3.9.2007
On location at Newby # 6-1, adjust weights, balance Jack. Well is flowing oil to tanks. Gun barrel and Separator fills, spilling to tanks.
3.8.2007
Finish connecting electricity to well, start Pump Jack on Newby # 6-1 to calibrate. Weights are out of sync. Shut down.
3.7.2007
On Newby # 6-1, set 40 HP Titan 228 Pump Jack with 74” stroke. Construct electrical network.
3.5.2007
Set separator, install flowline, continue work on facility at Newby # 6-1 location.
Move in Workover rig to the Grace # 25-1. Pull rods, pump, tubing, seat nipple and mud anchor out of hole. Pack well off, secure, leave location.
3.2.2007
Install seat, pump and rods into Newby # 6-1 well. Spaced pump, check action, hang well on Jack. Rig down Workover unit.
3.21.2007
Open well and bleed down Newby # 6-1 to atmosphere. Run in hole with casing swab. Hit fluid 2,600’. Run tubing into hole. Secure and shut in well.
2.28.2007
Move Workover unit onto Newby # 6-1 well. Casing swab well to 1,500’ and prepare for perforation. Rig up Electric Wireline unit, perforate Wilcox zone. Swab well with 16 runs down to 3,700’. Good show oil and gas. Shut in well.
2.6.2007
Replace Reeda Cable on the injection pump at the Disposal well on Hunn Lease.
8.8.2008
Enogex begin work on their pipeline, which affects our Hunn Lease. Click here.
1.11.2007
Finish building Sales Facility for Newby # 6-1 well.